Select Page

Chatooga Environmental Projects

Client Facility Start Date Project Duration
Chattooga Penn Bridge Road MSWL 1995 Quarterly Methane Monitoring 14
      Semi-Annual Groundwater Monitoring 14
    1996 GW Monitoring Plan Modification 1
      Methane Monitoring Plan Modification 1
    1998 Assessment Monitoring Plan 1
      Assessment of Corrective Measures 11
      Groundwater Well Installations 1
      Methane Well Installations 1
         
Average of Duration       5.5