Select Page

Chatham Environmental Projects



Client Facility Start Date Project Duration
Chatham Chevis Road C&D 1999 Semi-Annual Groundwater Monitoring 3
    2001 Quarterly Methane Monitoring 1
    2002 Groundwater Well Installation 1
    2003 Monthly Methane Monitoring 3
         
  City of Savannah – Dean Forest Road 1992 Semi-Annual Groundwater Monitoring 17
    1998 Assessment Monitoring Plan 1
    1999 Contaminant Assessment Plan 10
         
  Dillon C&D 1999 Semi-Annual Groundwater Monitoring 3
    2001 Quarterly Methane Monitoring 1
         
  Sharon Park C&D 1999 Semi-Annual Groundwater Monitoring 3
    2001 Quarterly Methane Monitoring 1
    2002 Groundwater Well Installation 1
         
  Thomas Avenue C&D 1999 Semi-Annual Groundwater Monitoring 3
    2001 Methane Well Installation 1
      Quarterly Methane Monitoring 1
    2002 Methane Well Installation 1
    2003 Monthly Methane Monitoring 3
         
  Wilmington Island C&D 1999 Semi-Annual Groundwater Monitoring 3
    2001 Groundwater Well Installation 1
      Methane Well Installation 1
      Quarterly Methane Monitoring 1
    2003 Monthly Methane Monitoring 3
         
Average of Duration       3